DOUGHERTY VALLEY HIGH SCHOOL EXPANSION
August 2016: Punchlist items in progress. Furniture installed. Network equipment is being installed. Staff is moving into building in early August.
May/June 2016: Project is on schedule for completion for start of school 2016. Furniture is on order, early August delivery anticipated.
March/April 2016: Exterior brick and stucco complete. Heating, Ventilation, and AC units on roof. Continuing interior utilities and finishes. Project is on schedule.
May/June 2015: Construction is under way.
March 2015: Award of bid for Classroom Building Addition.
February 2015: Classroom Building Addition project scheduled to rebid February 25, 2015.
December 2014: District facilities staff notifies neighbors of the upcoming project description and scope of work. The classroom building addition is scheduled to receive bids in January 2015.
July 2014: The DVHS classroom, lab and Green Technology expansion design drawings have been completed and were submitted to DSA mid-June. Expected approval is in about two months.
- Installation in outdoor science area for the CTE Green Technology Classes