skip to main content
July 2018
Modernization project Phase 1 began the day after school let out.  Site concrete work for ADA compliance, fencing, underground utility repair/replacement and roof replacement of half of the campus buildings will be completed prior to the start of school.  Partial exterior painting has been done but will be a work in progress and completed next summer 2019.
 
October 2017 
Drawings and specifications were submitted to the Department of State Architect (DSA) in fall 2017 and are scheduled to be approved in early 2018.
 
Summer 2019
  • New roofing and gutters on all buildings except Bldg A and five Relocatable Classrooms
  • Classroom updates including new flooring, ADA compliant sinks, new paint
  • Updated classroom technology including new data cabling, short-throw projectors, clock/PA system
  • Exterior paint
  • ADA modifications to bathrooms
  • New Fire Alarm system
  • Relocation of Relocatable Classrooms P1, P2 & P3
Montevideo Elementary Modernization
Construction Start Date: June 4, 2018
Construction End Date: August 1, 2019
Architect: HKIT Architects
 
Contractor: Sausal
Budget: $5.8 million
 
Project Manager: Erin Hirst